Sunday, March 30, 2014

TEST (historical March 2014)

March 8th 2014

More framing for fireplace.

Installed niche shelf in bathroom

March 15th 2014

Finish up framing for fireplace

March 26th 2014

Electrical runs for TV above fireplace and controls for blower into back bedroom.

Thursday, October 31, 2013

TEST (historical October 2013)

The pantry was pre-wired for a light, but it had an ugly little light fixture. The box that the light fixture attached to was right above the doorway. This location doesn’t leave a lot of options for something better. A normal ceiling light is too big to fit there. What we ended up with is a LED under counter type light bar. It fits and it’s LED. With a bit of hacking, it mounts to the existing box. Still not real pretty, but it is the under-stairs pantry.

We’re starting to think about what we want to do in the living room now that the hearth is gone and the walls are stripped of their paneling. We tore off the sheetrock on the wall where the hearth was located so we could see what we have to work with. We do want a gas fireplace installed here. To level out the floor, we had to add in some 3/8” particle board where the hearth was located.

We also spent time working on the hallway so that we could get it textured and primed.

Speaking of gas fireplaces, there are quite a few different brands and a few places around to look at them. Finding a dealer that will install and support in Clipper Mills and we’re comfortable is a bit of a challenge and that will determine what brand of fireplace we get.

Monday, September 30, 2013

Tiling toils

With the kitchen and bath cabinets in place, we schedule the counter top install. The installer came out with his son and they did a fantastic job installing the counter tops. Now the challenge will be to keep them clean.

Also, with the cabinets out of the living room, we pick up the pace on the demolition. Larry and Ben take great satisfaction ripping out the old carpet (from the 70’s?) and peeling the paneling off the walls. With all the debris out, it looks like we’re making progress.

The tub tile surround in the bathroom is finished, except for the grouting. It has taken 3 weekends. This is something that didn’t seem like it would be that time consuming, but all the back and forth measuring and cutting tiles take time as does stopping to mix up more thinset. After this, every project estimation will be multiplied by 3.

Saturday, August 31, 2013

A learning experience

August was a busy month. We were able to make it up every weekend and made great progress.

We learned how to spray texture on the walls and ceiling. Our test location was the kitchen since a lot of the walls in there get covered up by cabinets. Once you get the consistency of the texture correct, the real key seems to be the wait time before trying to knock it down. Waiting a bit longer is better than not long enough. Overall, it turned out pretty good. We were able to texture the kitchen, the hallway, the pantry and the bathroom. Once textured, we primed and painted the walls and ceiling.

The kitchen got a nice face lift. With the walls and ceiling done we installed the can lights and the cabinets.

With the cabinets out of the living room, we were able to start work there. Ben took a sledgehammer to the rock hearth. It was one well built hearth! The rock was held with lots of mortar that was strengthened further with chicken wire. Ben did let me take a few swings to relieve some of the stress from the bathroom tiling work. Thanks Ben!

Speaking of the bathroom … with the walls textured and painted we could start on the tub surround. The walls around the tub have plastic, cement board, and tile. Dealing with cement board was frustrating. On-line reports made it sound like you could score and snap it the same way you do sheetrock. Well, sort of. The score needs to be much deeper and you have to use a special tool. For large pieces it mostly worked. For small pieces, not so much. We did try power tools and dulled a circular saw blade after cutting about 6 inches. Same for a sawzall blade. Later we did find special (expensive) blades for circular saws for cutting cement board. We’ll be getting one of those before working with any more cement board.

With the cement board up, we worked on the tile. This was our first time working with tile so it was quite the learning experience. Cutting and fitting the tiles takes longer than expected. Square and plumb walls would be nice too. We did have to remove and re-do part of one wall because we didn’t get the tiles lined up right with the other wall.

Sandie found a new pass-time when a squirrel scampered up on the deck by the screen door and sat there. They had a bit of a stare down before the squirrel wisely scampered off.

Wednesday, July 31, 2013

The demolition continues

July 13th & 14th 2013

The kitchen was demolished. Well, all the cabinets were pulled and moved to the shed. We have grand plans of re-using the cabinets in the garage one day. These aren’t individual units like you get with pre-built type systems today, they’re one complete upper for each wall and similar large assemblies for the lowers. They appear to be made of maple and the construction looks pretty good. But, they don’t match our vision so out they go.

With the cabinetry gone, all the paneling was removed too. A lot of work scraping off old glue and sealing all the areas where the sheetrock paper was pulled off with the glue. Then a lot of joint compound to smooth out all the areas where the glue was scraped off. We’re making a couple of changes/improvements to the electrical now. Adding an outlet for the microwave, adding an outlet and switch for a garbage disposal. In addition to the garbage disposal switch, we’ll add another switch for under cabinet lighting. The kitchen lighting needs an update too. We pull out the old florescent tube lighting fixtures in the kitchen. The ceiling sheetrock was cut out for the fixture so instead of just a couple of small holes for wire, we had nice 3 ft. by 8 inch holes in the ceiling that need to be patched. In their place we cut holes for can lights. We’ll be using LED can lights.

Work continues on the bathroom. A vapor barrier was added to the floor, just in case we ever have a leak. The tub is now placed. After the rough plumbing is done, sheetrock is added. We use mold resistant sheetrock here.
[edit: If doing this over, we’d have put in sound insulation in the walls while they open just to isolate the bathroom a bit]

Barbara worked on the back bedroom, removing the “wainscoting” and pulling staples from the floor getting this room cleaned up.

Currently there’s a 3/8” particle board subfloor. Our plan is to replace that in the bathroom with 3/4” plywood and then add 1/4” plywood on top of the particle board everywhere else. This should provide a fairly even floor and give us the chance to screw things down.

Kent, the plumber, does our rough plumbing in the bath and kitchen. We also have him add a new valve for a fridge ice-maker. For everything he has to touch, he replaces the old cast iron pipe with either Pex or copper.

We have the hot water heater out so that we can work on the pantry. Kent installs new Pex lines for the hot water heater and leaves us with shark bite connectors so we can easily hook it back up once the pantry is finished. Speaking of the pantry. We fix up the sheetrock in there and add a disconnect for the hot water heater.

We’re finding that there are a lot of little details that we need to keep track of and be aware of as we work to rebuild the various rooms. If we forget something now, it will be much harder to do later in the process. An example is the light switch in the hall (for the hall light). The only kitchen light switch is over by the door that leads outside. It seemed like we needed another one and by expanding the hall switch box to a double gang box, a Insteon remote switch could be used to provide a second kitchen light switch. Doing this now while the bathroom sheetrock is out is easy, doing later after all the sheetrock is done would be difficult.