TEST (historical June 2014)
June 1st 2014
Starting to tile the kitchen floor. We get the bulk of the kitchen and hallway dry fitted.
June 7th 8th 2014
With all the dry fitting done, we can start installing the tile. The kitchen and hallway are finished.
June 21st, 22nd 2014
The bathroom floor tile in installed along with the pantry.
June 24th 2014
The fireplace is installed.
June 29th 30th 2014
The floor tile is grouted. The garbage disposal is wired up. The toilet is installed. The kitchen backsplash tile is started.