Tuesday, November 10, 2015

White walls

So for once, things pretty much went as planned for the weekend. Saturday morning we finished up masking the front bedroom and laid down the floor coverings. Then in the afternoon we sprayed texture on everything. The only real challenge was having to spray from the ladder to hit the peaks. Getting the mix consistency rightish is key and this time it was pretty good so we have a pretty consistent texture.

It was a bit chilly upstairs which helped keep us cool while working and I guess it was just warm enough that the texture was dry by Sunday morning. Sunday morning was spent sanding texture. The stairway needed the most work as that mix wasn’t right and it was rough and blobby (yes, blobby) and it needed a lot of sanding to make it look like knocked down texture. The bedrooms just needed a light pass to knock off a few random blobs and that went pretty quick. Then we started with the primer. The bedrooms, stairway, hallway, bathroom and closet were all primed. We finished up the closet with the last drops from the 5th (and last) can of primer.

Painting in the bathroom is a bit of challenge. Since we bumped the wall out, it now sits about 5 inches away from the beam. It takes a stubby paint brush to paint up in that 5 inch gap. We didn’t have one so I hacked the handle off a cheap 1” brush that we had and used that. It worked, but it’s still hard to see what been painted and what hasn’t when looking up into that 5 inch gap. I think we’ll start with that area next week just to get the hard part out of the way first.

It’s quite a transformation. The walls go from multi-colored with all the different drywall (original, new regular, new mold resistant) and all the joint compound spots to a nice even white primer color. After what seems like months of prep work, it’s really satisfying to see them like this.

And that’s all folks. We finished priming, cleaned up and left.

Where are we now?
weekend n+0 - drywall prep (October 17/18th did some, not as much as planned)
weekend n+1 - finish drywall prep for texture (October 23/24/25 - texturing started)
weekend n+2 - texture & prime (October 31st / November 1st - prepping for texture)
weekend n+3 - paint & start bathroom floor tile & finish bathroom electrical (textured and prime)
weekend n+4 - finish bathroom tile & re-install vanity & toilet
weekend n+5 - install doors & start knee wall framing
weekend n+6 - install laminate
weekend n+7 - finish laminate (baseboard & casing?)
weekend n+8 - knee wall work
weekend n+9 - knee wall work
weekend n+10 - knee wall work

Almost exactly 1 week behind this schedule. With the holidays rapidly approaching we’re going to see more slips.

  1. ukessaysreviews.com/essaypro-com-review

    Thursday, October 4, 2018 - 03:26:37

    Its impressive to know that you can cook this all so well.I, unfortunately, get rare time for baking because of another busy schedule. By the way, I love cupcakes. Thanks for sharing such a nice blog.

  2. For More Information Visit

    Monday, November 1, 2021 - 23:41:05

    I am very enjoyed for this blog. Its an informative topic. It help me very much to solve some problems. Its opportunity are so fantastic and working style so speedy.

  3. casinosite

    Thursday, February 2, 2023 - 20:36:00

    I’ve been searching for hours on this topic and finally found your post. I have read your post and I am very impressed. We prefer your opinion and will visit this site frequently to refer to your opinion. When would you like to visit my site?
    http://maps.google.nl/url?sa=t&url=https%3A%2F%2Ftotosafe.com

Add comment

Fill out the form below to add your own comments